You have been hired as a project manager for a bank. The banks wants you to design and develop custom online bill pay software so that its customers can pay their bills online.You are ready to begin the activity definition of your project. You have
identifies the scope statement, the WBS, and talked with the SME’s. In addition, for security reason, you have been informed that project team members must NOT have criminal history. In addition you’ve requested that the bank purchase the necessary transaction processing software, although the software is not yet available. What else do you need before you begin activity definition?

 Posted by Gctejwani on 12/29/2010 | Category: Project Management Interview questions | Views: 12138 | Points: 40
Select from following answers:
  1. Identify the milestone list
  2. Identify the activity attributes
  3. Identify the historical information on previous projects
  4. Identify the constraints and assumptions of the project
  5. All Above